Project: Shermnator   -  
            Listing of Entries
    (Please mouse-over any icon to get a description of that function).



Categories
  
Builder Name:David Sherman   -  
Project:   Vans - RV-9A   -   VIEW REPORTS
Total Hours:538.25
Start/Last Date:Dec 12, 2020 - Jun 01, 2025
Engine:Lycoming O-320 D2A
 
Friendly URL: https://eaabuilderslog.org?s=Shermnator

Home or Last Project Picture

Oct 15, 2022     Tank fab and left assembly - (24.5 hours)       Category: Wings
Football season is almost over, so I hope to start making good progress again. Because I don't have the room to do both wings at the same time, I have worked the left wing up to the fuel tank, and will then put it aside to do the same on the right wing. This way I can do all the pro seal on the tanks using just the one batch of product (limited shelf-life) and hopefully before it gets too cold outside.

So I did all the fabrication for both tanks and have the left tank finished except for the rear baffle. Switched out the wings on the jig to start on the right wing. Overall the tank and sealing wasn't too bad. Will see if I have any leaks - fingers crossed that I dont!

Shannon's dad, Sig, was there to help with with the end ribs.


 


NOTE: This information is strictly used for the EAA Builders Log project within the EAA organization.     -     Policy     -     © Copyright 2024 Brevard Web Pro, Inc.